Ramadan 2027 order timeline for shisha charcoal: latest order dates by transit
By Agus Setiawan, Production Supervisor · Last updated
Ask AI for an importer brief:
When to order shisha charcoal for Ramadan comes down to two numbers: your container's days from our gate to your port, and its size. The dates below count back from the expected first day of Ramadan 2027.
Latest order dates for Ramadan 2027, 20 ft and 40 ft
For Ramadan 2027, expected to begin on Mon 8 February 2027, a 20 ft that takes 35 days from our factory gate to discharge at your port must be ordered, deposit received, by Thu 12 November 2026, and a 40 ft by Thu 5 November 2026. Each date puts the container in port 14 days before the expected first day.
The ladder: order dates by days from gate to port
Find your days from our gate to discharge, and the row gives the Ramadan order deadline for a 20 ft and a 40 ft.
| Days from our gate to discharge | Order a 20 ft by | Order a 40 ft by | Leave the factory by |
|---|---|---|---|
| 14 | Wed 2 Dec 2026 | Wed 25 Nov 2026 | Mon 11 Jan 2027 |
| 21 | Wed 25 Nov 2026 | Wed 18 Nov 2026 | Mon 4 Jan 2027 |
| 28 | Tue 17 Nov 2026 | Tue 10 Nov 2026 | Mon 28 Dec 2026 |
| 35 | Thu 12 Nov 2026 | Thu 5 Nov 2026 | Mon 21 Dec 2026 |
| 42 | Thu 5 Nov 2026 | Thu 29 Oct 2026 | Mon 14 Dec 2026 |
| 49 | Thu 29 Oct 2026 | Thu 22 Oct 2026 | Mon 7 Dec 2026 |
| 56 | Thu 22 Oct 2026 | Thu 15 Oct 2026 | Mon 30 Nov 2026 |
Latest order dates for Ramadan 2027, counted back from discharge on Mon 25 January 2027
Find your row with your forwarder's quote
Your row comes from your forwarder's quote for days from gate-out here to discharge at your port, including the wait for a sailing and any transshipment. The page on transit times from Indonesia, and where the days go shows why a sailing schedule alone undercounts them. Between two rows, take the longer one: it gives the earlier date. Keyed on days, not ports, the ladder works for Turkey, Europe and North America as well as the Middle East.
What the ladder does not include
The ladder takes your forwarder's gate-to-discharge figure as its input and does not estimate it. It also leaves out the vessel booking, which is a separate gate, and it assumes a plain box or printed boxes ready by the packing day. It gives no per-port figures: no dated public source we could check covers the ports we looked at, and the transit that counts is your forwarder's.
The dates count back from an expected Ramadan start
Ramadan 2027 is expected to begin on Mon 8 February 2027, and Eid al-Fitr on 9 or 10 March 2027, in a projection by the UAE’s Astronomy Centre reported by The National (UAE) (thenationalnews.com, updated 6 October 2026). Moon sighting confirms it, and the first day can differ by a day between countries (The Conversation, theconversation.com, 17 February 2026). Discharge is targeted 14 days earlier, on Mon 25 January 2027: a planning margin, not free time at the port. Demurrage runs while the box sits in the terminal and detention once it has left, as the page on demurrage and detention once the container is discharged explains. Next year's dates are recalculated when the next Ramadan date is set.
The factory chain: production, a 14-day hold, packing
Four steps follow the deposit date, and they are our part of planning a charcoal container from loading to sea freight.
| Stage | 20 ft | 40 ft | How it is counted |
|---|---|---|---|
| Deposit received | order date | order date | production starts the next working day |
| Production | 15 working days | 20 working days | Monday to Friday, national holidays and collective leave out; excludes packaging, QC, booking |
| Weathering hold | 14 days | 14 days | calendar days; holidays do not lengthen it |
| Packing, QC and stuffing | 2 working days | 2 working days | one to two days; we plan with 2 |
| Gate-out | last packing day | last packing day | leaves our gate |
Factory chain, 20 ft vs 40 ft lead time
The hold is part of what Special Provision 978 requires before charcoal is packed, and stuffing day carries the temperature and headspace rules applied at stuffing.
Vessel booking is a separate gate
As of November 2026, vessel bookings for our containers, declared as “UN 1361, Class 4.2, Packing Group III”, to Jeddah, Aqaba and Beirut are currently confirmed the same day they are requested. Acceptance can change. For other lanes, the Gulf included, this page gives no figure and no forecast: check the dangerous-goods column of the Indonesia transit-time table and confirm with your forwarder before the deposit. Who books depends on which Incoterm puts the vessel booking with you or with us.
Worked example: a 20 ft on the 35-day row
A 20 ft with its deposit received on Thu 12 November 2026 runs:
- Production: Fri 13 November 2026 to Thu 3 December 2026.
- Weathering hold: to Thu 17 December 2026.
- Packing, QC and stuffing: Fri 18 December 2026 and Mon 21 December 2026; gate-out Mon 21 December 2026.
- Plus 35 days: discharge on Mon 25 January 2027, on or before the target of Mon 25 January 2027.
Holidays, Eid stock and planning the quantity
Holidays and collective leave inside the production window
These Indonesian national holidays and collective-leave days fall inside the production and packing windows behind the ladder. The factory closes on both, and the ladder counts them as non-working days:
- Christmas collective leave (cuti bersama), Thu 24 December 2026
- Christmas Day (national holiday), Fri 25 December 2026
- New Year’s Day (national holiday), Fri 1 January 2027
Source: the SKB 3 Menteri lists for 2026 and 2027 (Kemenko PMK, kemenkopmk.go.id, viewed 5 November 2026).
Eid stock travels in the pre-Ramadan container
The factory closes for about a week around Lebaran (Eid al-Fitr), whose Idul Fitri national holidays fall on Wed 10 March 2027 and Thu 11 March 2027. Eid restocking ordered during Ramadan runs into that Lebaran closure, so Eid stock belongs in the container you order before Ramadan.
Quantity, artwork and early stock
Ramadan stock planning starts from your own sales in the previous Ramadan, plus the Eid period and a buffer for a late vessel, rounded to full containers. What one box carries is set out in how many tons of charcoal a 20 ft or 40 ft holds, by shape. Send private-label artwork before the deposit: printing takes 2 weeks for a new design and 10 working days for an existing one. Stock that lands early should be kept dry and under cover.
Questions about Ramadan order dates
Why does a 40 ft container need an earlier order?
The 20 ft vs 40 ft lead time is the whole gap: 20 working days of production against 15, with the same hold and packing.
Is the weathering hold part of the production lead time?
No. The 14-day weathering hold runs after production and before packing, so it adds to the 15 or 20 working days.
Can I order for Eid after Ramadan has started?
Only with the Lebaran closure counted: such an order runs into the factory's closure of about a week around the Idul Fitri national holidays on Wed 10 March 2027 and Thu 11 March 2027.
What if my forwarder's transit quote changes?
Move to the row for the new figure. A longer quote after the deposit cuts into the 14-day discharge buffer; it does not move production.
Send your port and container size to the export desk on WhatsApp +628213924038, and the desk works out when to order shisha charcoal for Ramadan 2027 on your lane.
General planning information, not shipping, dangerous-goods or customs advice. Confirm transit and booking with your forwarder before the deposit.